  • docs/CommissioningPlan

    v201 v202  
    141141||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not the Argos swing arm, RR will be required on the SX side. AO support.||
    142142||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||8||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using the Argos swing arm and for different elevation angle tests, RR will be required on the SX side. AO support.||
     143||P2.65 / P3.12 / E1||[wiki:/docs/CommissioningPlan/P3.12 Star center Fourier mode images]||Day||1||C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using the Argos swing arm and for different elevation angle tests, RR will be required on the SX side. AO support.||
    143144||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||1||C3 + C4||Authorize SHARK-NIR on the SX side. RR mounted on the SX side. AO support.||
    144145||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Redo science detector calibrations]||Day||1||C3 + C4||-||
    145146||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Cryostat warm up check]||Day||2||C3||-||
    146 ||Total||(4 days of) contingency (15%) included within || ||32 days || || ||
     147||Total||(4 days of) contingency (15%) included within || ||33 days || || ||