Changes between Version 19 and Version 20 of docs/CommissioningPlan


Ignore:
Timestamp:
09/28/20 14:11:31 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v19 v20  
    8282 - From the LINC-NIRVANA commissioning experience, it is always better to keep the tools associated with a particular alignment together, to avoid looking for it in all the boxes there. Also, there MUST be a **living inventory** wiki page where everyone should note down what is taken and kept in the box/container.
    8383 -  Space required by SHARK-NIR at 3L is already mentioned to JC and CV. Later, we may need to specify the exact area.
     84 - For activities (P2.4-P2.8) which need the RR to be mounted on the SX side, the source should be a bright broad-band source (including also NIR wavelength). Perhaps, Ocean Optics would do. Also, if helpful, we may use a powerful (green) laser beam for initial alignment checks.
    8485
    8586== Commissioning Activity ==
     
    9596||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||0.5||C1||-||
    9697||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||1||C1||Liquid N2 fill in the cleanroom||
    97 ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Verification of the operability of the motors and light sources]||Day||0.5||C1||optical bench needed in the cleanrorm||
    98 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||4||C1||optical bench needed in the cleanrorm||
     98||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Verification of the operability of the motors and light sources]||Day||0.5||C1||optical bench needed in the cleanroom||
     99||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||4||C1||optical bench needed in the cleanroom||
    99100||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||1||C1||-||
    100101||Total||Contigency of 1 day|| ||9+1=10|| || ||
     
    111112||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||0.5||C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    112113||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features]||Day||0.5||C2||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO||
    113 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||2.5||C2 + C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO, the telescope need to move in elevation.||
     114||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||2.5||C2 + C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO, the telescope need to move in elevation||
    114115||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Nighttime acquisition and setting telescope collimation for night]||Night||0.5||C4||Support from LBTI/Arcetri on running SOUL AO||
    115116||Total||Contigency included within || ||11 days + half-night|| || ||