152 | | Phase 3 is further divided into 5 runs. Run 1 consists of essential common activities to every observing case. This will be the first to be tested on-sky. Run 2-5 blocks represent the nighttime technical commissioning of a set of 17 observing cases. For each of the observing cases, only one target will be tested. The contrast obtained from the data will be used as the merit function / success criterion. If contrast is not an option, a similar (or another) merit function will be used. After the completion of each of these runs, SHARK-NIR will be ready for Phase 4 (science verification) of the respective observing cases. |
153 | | |
154 | | It is important to note that Run 2-5 are interchangeable. It is currently sorted to have the software complexity in the increasing order and also considering the science interest. Note that "Run N" does not mean that it is the Nth visit to the observatory. For example, Run 1 can be completed in 1 or 2 visits to the observatory, depending on the allotted time. Note also that, for individual runs (2-5), the time taken for other basic activities (such as moving from one target to another, setting up the telescope, closing the AO loop, etc.) are not explicitly mentioned in the table. For example, we anticipate, it may take between 10-20 minutes to move and set the telescope and close the AO loop from one target to another (numbers from the LUCI overheads table). This extra duration required will be mostly covered in the rounding up of the total nights. |
| 151 | Phase 3 is further divided into 5 runs. Run 1 consists of essential common activities essential for every observing case. This will be the first to be tested on-sky. Run 2-5 blocks represent the nighttime technical commissioning of a set of 17 observing cases. For each of the observing cases, only one target will be tested. The contrast obtained from the data will be used as the merit function / success criterion. If contrast is not an option, a similar (or another) merit function will be used. After the completion of each of these runs, SHARK-NIR will be ready for Phase 4 (science verification) of the respective observing cases. |
| 152 | |
| 153 | It is important to note that Run 2-5 are interchangeable. It is currently sorted to have the software complexity in the increasing order and also considering the science interest. Note that "Run N" does not mean that it is the Nth visit to the observatory. For example, Run 1 can be completed in 1 or 2 visits to the observatory, depending on the allotted time. Note also that, for individual runs (2-5), the time taken for other basic activities (such as moving from one target to another, setting up the telescope, closing the AO loop, etc.) are not explicitly mentioned in the table. For example, we anticipate, it may take between 10-20 minutes to move and set the telescope and close the AO loop from one target to another (numbers from the LUCI overheads table). This extra duration required will be mostly covered within the 20% contingency and/or the rounding up of the total nights. |
241 | | |
242 | | ========= |
243 | | |
244 | | |
245 | | ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (nights)'''||'''Category'''||'''LBTO Support'''|| |
246 | | ||P3.0||[wiki:/docs/CommissioningPlan/P3.0 Large spatial scale instrument and telescope flat field]||Twilight||2 hours||C5 + C6||-|| |
247 | | ||P3.1||[wiki:/docs/CommissioningPlan/P3.1 Telescope control – sending preset]||Night||0.25||C5||-|| |
248 | | ||P3.2||[wiki:/docs/CommissioningPlan/P3.2 Telescope control – telescope mode, offset, and focal plane geometry estimation]||Night||0.25||C5||-|| |
249 | | ||P3.3||[wiki:/docs/CommissioningPlan/P3.3 SOUL-AO verification]||Night||1||C5 + C7||AO support|| |
250 | | ||P3.4||[wiki:/docs/CommissioningPlan/P3.4 Pupil alignment]||Night||0.25||C5 + C6||AO support|| |
251 | | ||P3.5||[wiki:/docs/CommissioningPlan/P3.5 Orient the coronagraphs]||Night||0.5||C5 + C6||AO support|| |
252 | | ||P3.6||[wiki:/docs/CommissioningPlan/P3.6 PSF Alignment]||Night||0.25||C5 + C6||AO support|| |
253 | | ||P3.7||[wiki:/docs/CommissioningPlan/P3.7 Verify the ADC rotation on sky]||Night||1||C5||AO support|| |
254 | | ||P3.8||[wiki:/docs/CommissioningPlan/P3.8 Checking field-stabilized mode/bearing rotation service]||Night||0.25||C5||AO support|| |
255 | | ||P3.9||[wiki:/docs/CommissioningPlan/P3.9 Internal TT loop working and performance]||Night||1||C5 + C7||AO support|| |
256 | | ||P3.10||[wiki:/docs/CommissioningPlan/P3.10 NCPA working and performance & checking for pupil shifts]||Night||3||C5 + C7||AO support|| |
257 | | ||P3.11||[wiki:/docs/CommissioningPlan/P3.11 Check the acquisition procedure]||Night||0.5||C5||AO support|| |
258 | | ||P3.12||[wiki:/docs/CommissioningPlan/P3.12 Star center Fourier mode images]||Night||1||C5 + C6||AO support|| |
259 | | ||P3.13||[wiki:/docs/CommissioningPlan/P3.13 Center the slit]||Night||2||C5||AO support|| |
260 | | ||P3.14||[wiki:/docs/CommissioningPlan/P3.14 Sky background]||Night||0.25||C5 + C6||-|| |
261 | | ||P3.15||[wiki:/docs/CommissioningPlan/P3.15 Astrometry plate scale and orientation]||Night||0.25||C5 + C6||AO support|| |
262 | | ||P3.16||[wiki:/docs/CommissioningPlan/P3.16 Flux calibration (off-centered target observation)]||Night||0.25||C5 + C6||AO support|| |
263 | | ||P3.17||[wiki:/docs/CommissioningPlan/P3.17 Instrumental throughput and absolute flux calibration]||Night||0.5||C5 + C6||AO support|| |
264 | | ||P3.18||[wiki:/docs/CommissioningPlan/P3.18 Atmospheric calibration and absolute flux calibration]||Night||0.5||C5 + C6||AO support|| |
265 | | ||P3.19||[wiki:/docs/CommissioningPlan/P3.19 Distortion map]||Night||0.5||C5 + C6||AO support|| |
266 | | ||P3.20||[wiki:/docs/CommissioningPlan/P3.20 Direct imaging + field stabilized mode testing]||Night||1||C5 + C7||AO support|| |
267 | | ||P3.21||[wiki:/docs/CommissioningPlan/P3.21 Direct imaging + pupil stabilized mode testing]||Night||1||C5 + C7||AO support|| |
268 | | ||P3.22||[wiki:/docs/CommissioningPlan/P3.22 Coronagraphic imaging + field stabilization mode testing]||Night||3||C5 + C7||AO support|| |
269 | | ||P3.23||[wiki:/docs/CommissioningPlan/P3.23 Coronagraphic imaging + pupil stabilization mode testing]||Night||3||C5 + C7||AO support|| |
270 | | ||P3.24||[wiki:/docs/CommissioningPlan/P3.24 Long-slit spectrograph mode testing]||Night||3||C5 + C7||AO support|| |
271 | | ||Total||Contingency of 3 nights (10%) || ||24+2 = 26|| || || |