Changes between Version 193 and Version 194 of docs/CommissioningPlan


Ignore:
Timestamp:
04/24/21 14:36:52 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v193 v194  
    88
    99== Introduction ==
    10 This commissioning planning document lays out and details the activities needed to bring SHARK-NIR online for 'shared-risk' scientific exploitation. The document incorporates activities starting from the unpacking of the boxes at the LBT mountain bay to the early science / science verification at its final destination on the LBT platform. Although called the commissioning document, it lists the pre-commissioning, commissioning, and science verification activities. The activities are classified into four phases.  Phase 1 and 2 are purely daytime activities. Phase 3 and 4 are nighttime activities (with little daytime activity anticipated). It is to be noted that Phase 3 activities are classified into observing cases (combinations of individual science observing possibilities using various coronagraphs and modes, we have 17 of them) and '''not''' according to the observing modes (direct imaging, coronagraphic imaging, long-slit spectroscopy) anymore.
    11 This allows starting Phase 4 (science verification) of those observing cases immediately after the competition of the respective Phase 3 commissioning run. See below for more details.
     10This commissioning planning document lays out and details the activities needed to bring SHARK-NIR online for 'shared-risk' scientific exploitation. The document incorporates activities starting from the unpacking of the boxes at the LBT mountain bay to the early science / science verification at its final destination on the LBT platform. Although called the commissioning document, it lists the pre-commissioning, commissioning, and science verification activities. The activities are classified into four phases.  Phase 1 and 2 are purely daytime activities. Phase 3 and 4 are nighttime activities (with little daytime activity anticipated). It is to be noted that Phase 3 activities are classified into observing cases (OC#, see the table below) and '''not''' according to the observing modes (direct imaging, coronagraphic imaging, long-slit spectroscopy) anymore. This allows commencing Phase 4 (science verification) of those observing cases immediately after the competition of the respective Phase 3 commissioning run. See below for more details.
    1211
    1312 **Phase 1**: We start by inspecting the boxes at LBT mountain bay, unpacking, and installing the instrument at the mountain lab (clean room) for alignment verification and functionality checks. All of these are daytime activities. [Pre-commissioning: Unpack, assemble, and clean-room verification]. This forms the content of the PSR-09 Preliminary Laboratory Integration & Test (I&T) Procedure (at LBT).
     
    2019
    2120== Observing Cases ==
     21Three observering modes of SHARK-NIR, namely direct imaging, coronagraphic imaging, long-slit spectroscopy, are classified into observing cases for the purpose of the commissioning. The observing cases are all the combinations of individual science observing possibilities using various coronagraphs and modes. We have 17 of them listed below.
    2222|| '''#'''      || '''observing_case''' ||     
    23 || OC1  ||      direct imaging - pupil stabilized ||
     23|| OC1  ||      Direct imaging - pupil stabilized ||
    2424|| OC2  ||      DBI - direct imaging - pupil stabilized ||
    25 || OC3  ||      direct imaging - field stabilized ||
     25|| OC3  ||      Direct imaging - field stabilized ||
    2626|| OC4  ||      DBI - direct imaging - field stabilized ||
    27 || OC5  ||      coro imaging - GL - field stabilized ||
    28 || OC6  ||      coro imaging - GL - pupil stabilized ||
    29 || OC7  ||      coro imaging - FQPM - pupil stabilized ||
    30 || OC8  ||      coro imaging - SP1 - pupil stabilized ||
     27|| OC5  ||      Coronagraphic imaging - GL - field stabilized ||
     28|| OC6  ||      Coronagraphic imaging - GL - pupil stabilized ||
     29|| OC7  ||      Coronagraphic imaging - FQPM - pupil stabilized ||
     30|| OC8  ||      Coronagraphic imaging - SP1 - pupil stabilized ||
    3131|| OC9  ||      DBI - coro imaging - SP1 - pupil stabilized ||
    32 || OC10 ||      coro imaging - SP2 - pupil stabilized ||
     32|| OC10 ||      Coronagraphic imaging - SP2 - pupil stabilized ||
    3333|| OC11 ||      DBI - coro imaging - SP2 - pupil stabilized ||
    34 || OC12 ||      coro imaging - SP3 - pupil stabilized ||
     34|| OC12 ||      Coronagraphic imaging - SP3 - pupil stabilized ||
    3535|| OC13 ||      DBI - coro imaging - SP3 - pupil stabilized ||
    3636|| OC14 ||      LSS (R~100) close companion ||
     
    3838|| OC16 ||      LSS (R~100) distant companion ||
    3939|| OC17 ||      LSS (R~800) close companion ||
    40 Note: OC16 and OC17 are LSS modes. Technically and SW-wise, there are no differences
    41 between them and (OC14 & OC15), and therefore not tested separately for Phase 3 nighttime commissioning.
     40Note that technically and software-wise, there are no differences
     41between (OC16 & OC17)  and (OC14 & OC15), and therefore not tested separately for Phase 3 nighttime commissioning.
     42
     43In the table above, the acronyms mean the following:
    4244{{{
    4345DBI - Dual Band Imaging.
     
    149151'''SHARK-NIR Location''': LBT platform. All nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.
    150152
     153Phase 3 is further divided into 5 runs. Run 1 consists of essential common activities to every observing case. This will be the first to be tested on-sky. Run 2-5 blocks represent the nighttime technical commissioning of a set of 17 observing cases. For each of the observing cases, only one target will be tested. The contrast obtained from the data will be used as the merit function / success criterion. If contrast is not an option, a similar (or another) merit function will be used. After the completion of each of these runs, SHARK-NIR will be ready for Phase 4 (science verification) of the respective observing cases.
     154
     155It is important to note that Run 2-5 are interchangeable. It is currently sorted to have the software complexity in the increasing order and also considering the science interest. Note that "Run N" does not mean that it is the Nth visit to the observatory. For example, Run 1 can be completed in 1 or 2 visits to the observatory, depending on the allotted time. Note also that, for individual runs (2-5), the time taken for other basic activities (such as moving from one target to another, setting up the telescope, closing the AO loop, etc.) are not explicitly mentioned in the table. For example, we anticipate, it may take between 10-20 minutes to move and set the telescope and close the AO loop from one target to another (numbers from the LUCI overheads table). This extra duration required will be mostly covered in the rounding up of the total nights.
     156
    151157Every evening of the nighttime commissioning, all the required calibrations (including dark, bias, flat-field, etc. for all the filters required) will be taken using the SHARK-NIR calibration unit.
     158
     159Seeing conditions definition: 
     160- good : <0.8"
     161- medium: 0.8"-1.2"
     162- bad: >1.2" - observable
     163
     164==== Run 1 ====
     165|| '''#'''      ||'''Activities '''|| '''Duration (hours)''' ||'''Seeing Conditions'''||
     166||  C1  || Large spatial scale instrument and telescope flat field (during Twilight)  ||  2 || twilight  ||     
     167||  C2  || Telescope control – sending preset  || 2 || bad      ||     
     168||  C3  || Telescope control – telescope mode, offset, and focal plane geometry estimation  || 2 || medium / bad        ||     
     169||  C4  || SOUL-AO verification  || 12 || good / medium ||     
     170||  C5  || Pupil alignment (for checking the pupil positon, and working of the script)  || 2 || bad     ||     
     171||  C6  || PSF Alignment  || 3 || good / medium ||     
     172||  C7  || Verify the ADC rotation on sky  || 4  || medium / bad        ||     
     173||  C8  || Checking field-stabilized mode/bearing rotation service  || 2 || bad ||     
     174||  C9  || Internal TT loop working and performance (diff mag and seeing conditions  || 8       || good / medium        ||     
     175||  C10 || NCPA working and performance & checking for pupil shifts  || 12      || medium (up to 1")    ||     
     176||  C11 || Check the acquisition procedure  || 2        || medium       ||     
     177||  C12 || Sky background         || 2 || bad   ||     
     178||  C13 || Astrometry plate scale and orientation  || 2 || good / medium        ||     
     179||  C14 || Distortion map  || 2 || good / medium        ||     
     180||              ||**Total time in nights (1 night = 8 hours) with 20% contingency**     || **8.55** nights ||   ||
     181||              || **Total duration rounded up**        || **9** nights ||      ||
     182
     183==== Run 2 ====
     184|| '''#'''      ||'''Activities / Observing Cases'''|| '''Duration (hours)''' ||'''Seeing Conditions'''||
     185||  OC1 || direct imaging - pupil stabilized  || 2.25  || medium / bad
     186||  OC2 || DBI - direct imaging - pupil stabilized  || 2.25  || medium / bad
     187||  OC3 || direct imaging - field stabilized  || 2.25  || medium / bad
     188||  OC4 || DBI - direct imaging - field stabilized  || 2.25  || medium / bad
     189||              ||**Total time in nights (1 night = 8 hours) with 20% contingency**  || **1.35** nights ||      ||
     190||              ||**Total duration rounded up**||       **2** nights ||         ||
     191'' Phase 4 science verification of the observing cases (1-4) can start after Run 2. ''
     192                               
     193==== Run 3 ====
     194|| '''#'''      ||'''Activities / Observing Cases'''|| '''Duration (hours)''' ||'''Seeing Conditions'''||
     195|| Test || Test / Correction following previous Run # || 4 ||bad||
     196|| C5   || Pupil alignment (for the GL and FQPM)        ||1||bad||
     197|| C6   || PSF Alignment (for the GL and FQPM)  ||2     ||good / medium||
     198|| E1   || Star center Fourier mode images      ||8     ||good / medium||
     199|| E2   || Flux calibration (off-centered target observation) (for the GL and FQPM)     ||2     ||good / medium||
     200|| E3   || Instrumental throughput and absolute flux calibration (for a set of filters) ||2     ||bad||
     201|| OC5  || coro imaging - GL - field stabilized  ||3||good / medium||
     202|| OC6  || coro imaging - GL - pupil stabilized ||3||good / medium||
     203|| OC7  || coro imaging - FQPM - pupil stabilized       ||3     ||good / medium||
     204||              ||**Total time in nights (1 night = 8 hours) with 20% contingency**  || **4.2** nights ||       ||
     205||              ||**Total duration rounded up**||       **5** nights ||         ||
     206'' Phase 4 science verification of the observing cases (5-6*) can start after Run 3     ''     
     207                               
     208
     209==== Run 4 ====
     210|| '''#'''      ||'''Activities / Observing Cases'''|| '''Duration (hours)''' ||'''Seeing Conditions'''||
     211|| Test || Test / Correction following previous Run #   || 4    || bad  ||
     212|| C5   || Pupil alignment (For SP, SP-X, SP-Y) || 1    || bad  ||
     213|| C6   || PSF Alignment (For SP, SP-X, SP-Y)   || 2    || good / medium  ||
     214|| E4        || Orient the coronagraphs (Orient the apodizers)  || 1    || bad  ||
     215|| E2   || Flux calibration (off-centered target observation for the SP, SP-X, SP-Y)    || 2    || good / medium  ||
     216|| OC8  || coro imaging - SP1 - pupil stabilized        || 3    || good / medium  ||
     217|| OC9  || DBI - coro imaging - SP1 - pupil stabilized  || 3    || good / medium  ||
     218|| OC10 || coro imaging - SP2 - pupil stabilized        || 3    || good / medium  ||
     219|| OC11 || DBI - coro imaging - SP2 - pupil stabilized  || 3    || good / medium  ||
     220|| OC12 || coro imaging - SP3 - pupil stabilized        || 3    || good / medium  ||
     221|| OC13 || DBI - coro imaging - SP3 - pupil stabilized  || 3    || good / medium  ||
     222||              ||**Total time in nights (1 night = 8 hours) with 20% contingency**  || **4.2** nights ||       ||
     223||              ||**Total duration rounded up**||       **5** nights ||         ||
     224'' Phase 4 science verification of the observing cases (8-13*) can start after Run 4''
     225                                       
     226                               
     227==== Run 5 ====
     228|| '''#'''      ||'''Activities / Observing Cases'''|| '''Duration (hours)''' ||'''Seeing Conditions'''||
     229|| Test || Test / Correction following previous Run #     ||3  ||bad  ||
     230|| C6   || PSF Alignment  (for the SLIT-1 and SLIT-2)  ||2  ||good / medium  ||
     231|| E5           || Center the slit  ||8  ||medium / bad  ||
     232|| E6           || Atmospheric calibration and absolute flux calibration  ||2  ||good / medium  ||
     233|| OC14 || LSS (R~100) companion (0.175"<distance<0.35")  ||2.5  ||good / medium  ||
     234|| OC15 || LSS (R~800) companion (distance > 0.35")  ||2.5  ||good / medium  ||
     235||              ||**Total time in nights (1 night = 8 hours) with 20% contingency**  || **3** nights ||         ||
     236||              ||**Total duration rounded up**||       **3** nights ||         ||
     237'' Phase 4 science verification of the observing cases (14-17*) can start after Run 5''
     238                               
     239- ** Net Phase 3 Nights Requested = 24 
     240- When Phase 4 science verification completes, SHARK-NIR can be offered to public under 'shared-risk'!!!               
     241
     242=========
     243
     244
    152245||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (nights)'''||'''Category'''||'''LBTO Support'''||
    153246||P3.0||[wiki:/docs/CommissioningPlan/P3.0 Large spatial scale instrument and telescope flat field]||Twilight||2 hours||C5 + C6||-||