Changes between Version 190 and Version 191 of docs/CommissioningPlan
- Timestamp:
- 02/05/21 18:20:29 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v190 v191 108 108 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Redo science detector calibrations]||Day||1||C3 + C4||-|| 109 109 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Cryostat warm up check]||Day||2||C3||-|| 110 ||Total||(4 days of) contingency (15%) included within || || 28days || || ||110 ||Total||(4 days of) contingency (15%) included within || ||32 days || || || 111 111 112 112