91 | | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||-|| |
92 | | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes and their visual inspection]||Day||0.5||C1||crane operator to lift and move containers/boxes, 1-2 crew to support unpacking and moving|| |
93 | | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Install the instrument in the cleanroom with its electronics cabinet]||Day||0.5||C1||crane operator to lift and move containers/boxes, 1-2 crew to support installation on the mechanical structure|| |
94 | | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, and connect to LBT network]||Day||0.5||C1||support to connect to LBT network? Any electronics support?|| |
| 91 | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay)|| |
| 92 | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes and their visual inspection]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support unpacking and moving|| |
| 93 | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Install the instrument in the cleanroom with its electronics cabinet]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure|| |
| 94 | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, and connect to LBT network]||Day||0.5||C1||support to connect to LBT network, IT support to install/set the computers near Control room|| |
105 | | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1+1+1||C1||1 day for preparation, 1 day for lifting, and 1 day contigency|| |
106 | | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1||C2||Verify the working of emergency button|| |
| 105 | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1 (preparation) + 1 (lift-off) + 1 (contigency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed infont of the gregorian focal-station SX|| |
| 106 | ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1||C2||support to verify the working of emergency button/stop|| |
108 | | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriter|| |
109 | | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||1+1||C2||Mounting RR on the SX side. Support from LBTI?|| |
110 | | ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Synergy with LBTI AO system test]||Day||0.5||C2||Mounting RR on the SX side. Support from LBTI for AO running|| |
111 | | ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||0.5||C3||Mounting RR on the SX side, Support from LBTI for AO running|| |
112 | | ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features]||Day||0.5||C2||Support from LBTI for AO running|| |
113 | | ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||2.5||C2 + C3||Support from LBTI for AO running|| |
114 | | ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Nighttime acquisition and setting telescope collimation for night]||Night||0.5||C4||Support from LBTI for AO running|| |
| 108 | ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriter, support from LBT SW team|| |
| 109 | ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||1+1||C2||working platform installed infont of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO|| |
| 110 | ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Synergy with LBTI AO system test]||Day||0.5||C2||working platform installed infont of the gregorian focal-station SX, Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO|| |
| 111 | ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||0.5||C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO|| |
| 112 | ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features]||Day||0.5||C2||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO|| |
| 113 | ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||2.5||C2 + C3||Mounting RR on the SX side. Support from LBTI/Arcetri on running SOUL AO, the telescope need to move in elevation.|| |
| 114 | ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Nighttime acquisition and setting telescope collimation for night]||Night||0.5||C4||Support from LBTI/Arcetri on running SOUL AO|| |