docs/CommissioningPlan
v186 v187 92 92 ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1 + C4||Liquid N2 refill is required in the cleanroom.|| 93 93 ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required.|| 94 ||Total||( 3 days of) contingency (20%) included within|| ||16|| || ||94 ||Total||(2 days of) contingency (10%) included within|| ||16|| || || 95 95 96 96 === Phase 2 (Pre-commissioning)===