Changes between Version 185 and Version 186 of docs/CommissioningPlan
- Timestamp:
- 02/05/21 12:12:41 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v185 v186 106 106 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.|| 107 107 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||1||C3 + C4||Authorize SHARK-NIR on the SX side. RR mounted on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.|| 108 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations and total check up]||Day||1||C3 + C4||-||108 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Redo science detector calibrations]||Day||1||C3 + C4||-|| 109 109 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Cryostat warm up check]||Day||2||C3||-|| 110 110 ||Total||(4 days of) contingency (15%) included within || ||28 days || || ||