    4 This document lays out the procedures and performance requirements for commissioning the SHARK-NIR instrument. Specifically, it lists the on-telescope activities needed to bring SHARK-NIR online for scientific exploitation starting from unpacking the boxes at LBT with the exception of the instrument installation at the LBT Bent Gregogian Central focal station.
     4This document lays out the procedures and performance requirements for commissioning the SHARK-NIR instrument. Specifically, it lists the on-telescope activities needed to bring SHARK-NIR online for scientific exploitation starting from unpacking the boxes at LBT.
    55
    66The commissioning is broadly divided into three phases:
    7  **Phase 1**: We start from inspecting the boxes at LBT mountain bay, unpacking and installing the instrument at the mountain lab for alignment verification and functionality checks. All of these are daytime activities.
    8 
    9  **Phase 2**: The activities after the installation of SHARK-NIR at the SX central bent Gregorian focus of LBT to the acquirement of the first nighttime telescope collimation model of the instrument form the Phase 2. Most of the activities are daytime. The only nighttime activity is to check the pointing, acquisition sequence and getting the first nighttime telescope collimation model for SHARK-NIR.
     7 **Phase 1**: We start from inspecting the boxes at LBT mountain bay, unpacking, and installing the instrument at the mountain lab for alignment verification and functionality checks. All of these are daytime activities.
     8
     9 **Phase 2**: The activities starting from the installation of SHARK-NIR at the SX central bent Gregorian focus of LBT to the acquirement of the first nighttime telescope collimation model of the instrument form the Phase 2. Most of the activities are daytime. The only nighttime activity is to check the pointing, acquisition sequence, and getting the first nighttime telescope collimation model for SHARK-NIR.
    1010
    1111 **Phase 3**: Phase 3 of the commissioning starts from sending preset to the telescope to testing individual SHARK-NIR observation modes for performance to the total SHARK-NIR performance. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for Science Verification.
    1212
    13 Note that the corresponding evolving doc in SHARK-NIR Dropbox folder is **SHARK-NIR-INAFP-COM-001_CommissioningPlan.docx**. There is also an excel file listing the activities titled **SHARK-NIR-INAFP-COM-002_CommissioningActivityList.xlsx**.
     13Note that the corresponding evolving doc in the SHARK-NIR Dropbox folder is **SHARK-NIR-INAFP-COM-001_CommissioningPlan.docx**. There is also an excel file listing the activities titled **SHARK-NIR-INAFP-COM-002_CommissioningActivityList.xlsx**.
    1414
    1515== Applicable Documents ==
     
    1818|| AD1 || SHARK-NIR Schedule || SHARK-NIR-INAFP-SCH-001_Issue 1.2.pdf ||
    1919|| AD2 || SHARK-NIR SW ICD || SHARK-NIR-INAFP-SW-ICD-FDR Issue 0.4 ||
    20 || AD3 || SHARK-NIR Installation Plan || SHARK-NIR-INAFP-IP-001 Issue 0.1 ||
     20|| AD3 || SHARK-NIR Installation Plan || SHARK-NIR-INAFP-IP-001 Issue 0.2 ||
    2121|| AD4 || SHARK-NIR Calibrations || SHARK-NIR-INAFP-MAN-004 ||