  • docs/CommissioningPlan

    v178 v179  
    103103||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||2||C3||Authorize SHARK-NIR. Permission to SX ASM and LBTI AO. Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter. Support from the LBT SW team.||
    104104||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||3||C3||Working platform installed in front of the Gregorian focal-station SX, Argos swing arm and calibration source on SX side. Support from the LBTI team.||
    105 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not Argos swing arm, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team on running SOUL AO.||
     105||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not Argos swing arm, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team on running SOUL AO.||
    106106||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
    107 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||1||C3||Authorize SHARK-NIR on the SX side. RR mounted on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
    108 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations and total check up]||Day||1||C3||-||
     107||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||1||C3 + C4||Authorize SHARK-NIR on the SX side. RR mounted on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
     108||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations and total check up]||Day||1||C3 + C4||-||
    109109||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Cryostat warm up check]||Day||2||C3||-||
    110110||Total||(4 days of) contingency (15%) included within || ||28 days || || ||