    9090||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Check the working of the internal tip-tilt loop]||Day||1||C1||Liquid N2 refill is required in the cleanroom.||
    9191||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Verification of the operability of the motors & light sources and looking for filter defects/artifacts]||Day||1.5||C1||Liquid N2 refill is required in the cleanroom.||
    92 ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1||Liquid N2 refill is required in the cleanroom.||
     92||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1 + C4||Liquid N2 refill is required in the cleanroom.||
    9393||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required.||
    9494||Total||(3 days of) contingency (20%) included within|| ||16|| || ||