Changes between Version 175 and Version 176 of docs/CommissioningPlan
- Timestamp:
- 02/04/21 16:43:35 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v175 v176 91 91 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Verification of the operability of the motors & light sources and looking for filter defects/artifacts]||Day||1.5||C1||Liquid N2 refill is required in the cleanroom.|| 92 92 ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1||Liquid N2 refill is required in the cleanroom.|| 93 ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required ||93 ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required.|| 94 94 ||Total||(3 days of) contingency (20%) included within|| ||16|| || || 95 95