  • docs/CommissioningPlan

    v15 v16  
    103103'''SHARK-NIR Location''' : LBT platform
    104104||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    105 ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1+1+1|||C2||I day for preparation, 1 day for lifting, and 1 day contigency||
    106 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1|||C2||Verify the working of emergency button||
     105||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1+1+1||C1||1 day for preparation, 1 day for lifting, and 1 day contigency||
     106||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1||C2||Verify the working of emergency button||
    107107||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and performance]||Day||0.5||C2||-||
    108108||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||0.5||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriter||