Changes between Version 158 and Version 159 of docs/CommissioningPlan


Ignore:
Timestamp:
02/04/21 12:44:32 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v158 v159  
    104104||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||3||C3||Working platform installed in front of the Gregorian focal-station SX, Argos swing arm and calibration source on SX side. Support from the LBTI team.||
    105105||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not Argos swing arm, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team on running SOUL AO.||
    106 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||?||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
    107 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||?||C3||Authorize SHARK-NIR on the SX side. RR mounted on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
     106||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
     107||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||1||C3||Authorize SHARK-NIR on the SX side. RR mounted on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
    108108||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations and total check up]||Day||1||C3||-||
    109109||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||?||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
    110110||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3||-||
    111 ||Total||(4 days of) contingency included within || ||22 + ??? days || || ||
     111||Total||(4 days of) contingency included within || ||28 days || || ||
    112112
    113113