    7676== Commissioning Activity ==
    77 In this section, you can see all the commissioning activities listed in chronological order. If you click the individual activity, you can see more details of it. 8 hours is considered as the duration of day/night. Of course, depending on the month of the year, we will modify the actual number of days required for that specific commissioning run. From experience at the LBT, for the daytime activities at the telescope platform, the telescope can be handed over around 9 am local time. And we need to hand it over back to the LBT ~2 hours before the sunset (unless we have the first half of the night Or full night). Note that the durations mentioned in this document will not match with that of AD4 for the same activities.
     77In this section, you can see all the commissioning activities listed in chronological order. If you click the individual activity, you can see more details of it. __8 hours is considered as the duration of a day/night__. It is to be noted that the phases do not correspond to the commissioning runs. The various commissioning runs with the list of activities to be performed (derived from this document) will be decided at a later point in time. Of course, depending on the month of the year, we will modify the actual number of days required for that specific commissioning run. From commissioning experience at the LBT, for the daytime activities at the telescope platform, the telescope can be handed over around 9 am local time. And we need to hand it over back to the LBT ~2 hours before the sunset (unless we have the first half of the night or full night and to be negotiated with the telescope operator). Note that the duration of the individual activities mentioned in this document will not match with that of AD4 for the same activities.
    7878
    7979=== Phase 1 (Pre-commissioning)===
    80 '''SHARK-NIR Location''': LBT mountain bay and clean room (Some of the activities may run in parallel). All daytime activities. In the cleanroom, usually, there are no restrictions on daytime or nighttime activity.
     80'''SHARK-NIR Location''': LBT mountain bay and clean room. Some of the activities may run in parallel. All daytime activities. In the cleanroom, usually, there are no restrictions on daytime or nighttime activity.
    8181||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||                     
    8282||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support moving containers/boxes.||
     
    9595
    9696=== Phase 2 (Pre-commissioning)===
    97 '''SHARK-NIR Location''': LBT platform (Some of the activities may run parallel). All daytime activities.
     97'''SHARK-NIR Location''': LBT platform. Some of the activities may run in parallel. All daytime activities.
    9898||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    9999||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of the SHARK-NIR at LBT platform - 1]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR. Crane operator (mountain bay, LBT platform). Safety officer. Working platform installed in front of the Gregorian focal-station SX. Hatch door SX on the UIAP platform removed. Support for the installation of electronics in the LBTO cabinet. Kindly check the installation document, AD3, for more details||
     
    163163
    164164To be added:
    165  1. Other performance activities, if any
    166  2. Look-up tables, if any
     165 1.  Look-up tables, if any
    167166
    168167== Comments ==
    169168
    170 === MDP
    171 - all operation that should be supported by **control software** automated procedures should be defined by the responsible person with software person in copy or accordance with software department (better) (e.g., P1.8 and P1.9)
    172  
    173 === Reminders