Changes between Version 153 and Version 154 of docs/CommissioningPlan
- Timestamp:
- 02/03/21 19:06:29 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v153 v154 109 109 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||?||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.|| 110 110 ||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3||-|| 111 ||Total|| Contingency included within || ||36days || || ||111 ||Total||(4 days of) contingency included within || ||22 + ??? days || || || 112 112 113 113