  • docs/CommissioningPlan

    v150 v151  
    9797'''SHARK-NIR Location''': LBT platform (Some of the activities may run parallel). All daytime activities.
    9898||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    99 ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of the SHARK-NIR at LBT platform - 1]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document, AD3, for more details.||
    100 ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of the SHARK-NIR at LBT platform - 2]||Day||2||C2||Support for the installation and checking of electronics cabinets, cabling, and their checking, safety officer, working platform installed in front of the Gregorian focal-station SX, check the installation document, AD3, for more details.||
    101 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C3||support to verify the working of emergency button/stop?, Testing the electronics and SW working of the knob (motor) controlling the cooling flow rate, Liquid Nitrogen fill.||
     99||P2.0A||[wiki:/docs/CommissioningPlan/P2.0A Installation of the SHARK-NIR at LBT platform - 1]||Day||2(preparation) + 2(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR. Crane operator (mountain bay, LBT platform). Safety officer. Working platform installed in front of the Gregorian focal-station SX. Hatch door SX on the UIAP platform removed. Support for the installation of electronics in the LBTO cabinet. Kindly check the installation document, AD3, for more details||
     100||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of the SHARK-NIR at LBT platform - 2]||Day||2||C2||1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. Safety officer. Kindly check the installation document, AD3, for more details.||
     101||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C3||Testing the working of the knob (motor) controlling the cooldown. Liquid Nitrogen fill. Vacuum pump.||
    102102||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||2||C3||-||
    103 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||1||C3||Authorize SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team||
    104 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||3||C3||working platform installed in front of the Gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO||
    105 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not Argos swing arm, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team on running SOUL AO||
    106 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||?||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO||
    107 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||?||C3||Mounting RR on the SX side. Support on running SOUL AO||
     103||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||1||C3||Authorize SHARK-NIR. Permission to SX ASM and LBTI AO. Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter. Support from the LBT SW team.||
     104||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||3||C3||Working platform installed in front of the Gregorian focal-station SX, Argos swing arm and calibration source on SX side. Support from the LBTI team.||
     105||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not Argos swing arm, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team on running SOUL AO.||
     106||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||?||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
     107||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||?||C3||Authorize SHARK-NIR on the SX side. RR mounted on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
    108108||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations and total check up]||Day||1||C3||-||
    109 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||?||C3 + C4||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
     109||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||?||C3 + C4|Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO.||
    110110||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3||-||
    111111||Total||Contingency included within || ||36 days || || ||