docs/CommissioningPlan
v149 v150 100 100 ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0B Installation of the SHARK-NIR at LBT platform - 2]||Day||2||C2||Support for the installation and checking of electronics cabinets, cabling, and their checking, safety officer, working platform installed in front of the Gregorian focal-station SX, check the installation document, AD3, for more details.|| 101 101 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C3||support to verify the working of emergency button/stop?, Testing the electronics and SW working of the knob (motor) controlling the cooling flow rate, Liquid Nitrogen fill.|| 102 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day|| 1||C3||-||102 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||2||C3||-|| 103 103 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||1||C3||Authorize SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the fitswriter, support from LBT SW team|| 104 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day|| 2+1||C3||working platform installed in front of the Gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO||104 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||3||C3||working platform installed in front of the Gregorian focal-station SX, Mounting RR on the SX side. Support on running SOUL AO|| 105 105 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 SOUL AO system test]||Day||5||C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. If not Argos swing arm, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team on running SOUL AO|| 106 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day|| 5+5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO||107 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day|| 3||C3||Mounting RR on the SX side. Support on running SOUL AO||106 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||?||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO|| 107 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||?||C3||Mounting RR on the SX side. Support on running SOUL AO|| 108 108 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations and total check up]||Day||1||C3||-|| 109 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day|| 3||C3 + C4||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||109 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||?||C3 + C4||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation|| 110 110 ||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3||-|| 111 111 ||Total||Contingency included within || ||36 days || || ||