Changes between Version 14 and Version 15 of docs/CommissioningPlan
- Timestamp:
- 09/28/20 12:11:18 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v14 v15 102 102 === Phase 2 === 103 103 '''SHARK-NIR Location''' : LBT platform 104 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (d )'''||days||'''Category'''||'''LBTO Support'''||104 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''|| 105 105 ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1+1+1|||C2||I day for preparation, 1 day for lifting, and 1 day contigency|| 106 106 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1|||C2||Verify the working of emergency button||