  • docs/CommissioningPlan

    v14 v15  
    102102=== Phase 2 ===
    103103'''SHARK-NIR Location''' : LBT platform
    104 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (d)'''||days||'''Category'''||'''LBTO Support'''|| 
     104||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    105105||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||1+1+1|||C2||I day for preparation, 1 day for lifting, and 1 day contigency||
    106106||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1|||C2||Verify the working of emergency button||