  • docs/CommissioningPlan

    v148 v149  
    9292||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1||Liquid N2 refill is required in the cleanroom.||
    9393||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required||
    94 ||Total||Contingency included within|| ||13.5|| || ||
     94||Total||(3 days of) contingency included within|| ||16|| || ||
    9595
    9696=== Phase 2 (Pre-commissioning)===