docs/CommissioningPlan
v148 v149 92 92 ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1||Liquid N2 refill is required in the cleanroom.|| 93 93 ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required|| 94 ||Total|| Contingency included within|| ||13.5|| || ||94 ||Total||(3 days of) contingency included within|| ||16|| || || 95 95 96 96 === Phase 2 (Pre-commissioning)===