82 | | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support moving|| |
83 | | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes, their visual inspection, and mounting the units on the handling]||Day||1||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support unpacking and moving|| |
84 | | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet]||Day||1.5||C1||crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure, Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.|| |
85 | | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||1||C1||support to connect to LBT network, IT support to install/set the workstations in the proper location|| |
| 82 | ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support moving containers/boxes.|| |
| 83 | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes, their visual inspection, and mounting the units on the handling]||Day||1||C1||Crane operator (mountain bay) to lift and move stuff. 1-2 crew to support unpacking and moving.|| |
| 84 | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet]||Day||1.5||C1||Crane operator to lift and move stuff (mountain bay and/or cleanroom). 1-2 crew to support installation procedure (mountain bay and/or cleanroom). Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. Optical bench and access to the clean tent.|| |
| 85 | ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||1||C1||IT support to install/set the workstations in the proper location, connect to the LBT network. LBTO SW support may be needed.|| |
87 | | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||1||C1||Liquid N2 fill in the cleanroom|| |
88 | | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Check the working of the internal NCPA routine]||Day||0.5||C1||optical bench needed in the cleanroom, Liquid N2 fill in the cleanroom|| |
89 | | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||4||C1||optical bench needed in the cleanroom, Liquid N2 fill in the cleanroom|| |
90 | | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Check the working of the internal tip-tilt loop]||Day||1||C1||Liquid N2 fill in the cleanroom|| |
91 | | ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Verification of the operability of the motors & light sources and looking for filter defects/artifacts]||Day||1.5||C1||LBTO SW support maybe required, Liquid N2 fill in the cleanroom|| |
92 | | ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1||Liquid N2 fill in the cleanroom|| |
93 | | ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||-|| |
| 87 | ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||1||C1||Liquid N2 refill is required in the cleanroom. Vacuum pump and support for cooling down the cryostat.|| |
| 88 | ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Check the working of the internal NCPA routine]||Day||0.5||C1||Liquid N2 refill is required in the cleanroom.|| |
| 89 | ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||4||C1||Liquid N2 refill is required in the cleanroom.|| |
| 90 | ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Check the working of the internal tip-tilt loop]||Day||1||C1||Liquid N2 refill is required in the cleanroom.|| |
| 91 | ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Verification of the operability of the motors & light sources and looking for filter defects/artifacts]||Day||1.5||C1||Liquid N2 refill is required in the cleanroom.|| |
| 92 | ||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Science detector calibrations]||Day||1||C1||Liquid N2 refill is required in the cleanroom.|| |
| 93 | ||P1.12||[wiki:/docs/CommissioningPlan/P1.12 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||Liquid N2 refill is required in the cleanroom. LBTO SW support may be required|| |