Changes between Version 138 and Version 139 of docs/CommissioningPlan
- Timestamp:
- 02/02/21 11:55:18 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v138 v139 105 105 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5+5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO|| 106 106 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C3||Mounting RR on the SX side. Support on running SOUL AO|| 107 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations repeat]||Day||2||C3||-||107 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations and total check up]||Day||1||C3||-|| 108 108 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||3||C3 + C4||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation|| 109 109 ||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3||-|| 110 ||Total||Contingency included within || ||3 7days || || ||110 ||Total||Contingency included within || ||36 days || || || 111 111 112 112