Changes between Version 138 and Version 139 of docs/CommissioningPlan


Ignore:
Timestamp:
02/02/21 11:55:18 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v138 v139  
    105105||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5+5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO||
    106106||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C3||Mounting RR on the SX side. Support on running SOUL AO||
    107 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations repeat]||Day||2||C3||-||
     107||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations and total check up]||Day||1||C3||-||
    108108||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||3||C3 + C4||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
    109109||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3||-||
    110 ||Total||Contingency included within || ||37 days || || ||
     110||Total||Contingency included within || ||36 days || || ||
    111111