    9090||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||1||C1||Liquid N2 fill in the cleanroom||
    9191||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||LBTO SW support maybe required, Liquid N2 fill in the cleanroom||
    92 ||Total||Contingency included within|| ||12.5|| || ||
     92||P1.11||[wiki:/docs/CommissioningPlan/P1.11 Check the working of the internal NCPA routine and looking for filter defects/artifacts]||Day||1||C1||Liquid N2 fill in the cleanroom||
     93||Total||Contingency included within|| ||13.5|| || ||
    9394
    9495=== Phase 2 (Pre-commissioning)===
     
    104105||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5+5||C3 + C4||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO||
    105106||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C3||Mounting RR on the SX side. Support on running SOUL AO||
    106 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Looking for filter defects/artifacts + Science detector calibrations repeat]||Day||2||C3||-||
     107||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Science detector calibrations repeat]||Day||2||C3||-||
    107108||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||3||C3 + C4||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
    108109||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3||-||