Changes between Version 136 and Version 137 of docs/CommissioningPlan
- Timestamp:
- 02/02/21 10:59:27 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v136 v137 96 96 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''|| 97 97 ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform - 1]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document, AD3, for more details.|| 98 ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform - 2]||Day|| 1||C2||Support for the installation and checking of electronics cabinets, cabling, and their checking, safety officer, working platform installed in front of the Gregorian focal-station SX, check the installation document, AD3, for more details.||98 ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform - 2]||Day||2||C2||Support for the installation and checking of electronics cabinets, cabling, and their checking, safety officer, working platform installed in front of the Gregorian focal-station SX, check the installation document, AD3, for more details.|| 99 99 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument, basic check, initiate cryostat cool down]||Day||1||C3||support to verify the working of emergency button/stop?, Testing the electronics and SW working of the knob (motor) controlling the cooling flow rate, Liquid Nitrogen fill.|| 100 100 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and functioning]||Day||1||C3||-|| … … 107 107 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||3||C3 + C4||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation|| 108 108 ||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C3||-|| 109 ||Total||Contingency included within || ||3 6days || || ||109 ||Total||Contingency included within || ||37 days || || || 110 110 111 111