Changes between Version 135 and Version 136 of docs/CommissioningPlan
- Timestamp:
- 02/02/21 10:54:54 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v135 v136 82 82 ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support moving|| 83 83 ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes, their visual inspection, and mounting the units on the handling]||Day||1||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support unpacking and moving|| 84 ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet]||Day|| 0.5||C1||crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure, Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.||84 ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet]||Day||1||C1||crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure, Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.|| 85 85 ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network]||Day||0.5||C1||support to connect to LBT network, IT support to install/set the workstations in the proper location|| 86 ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day|| 0.5||C1||-||86 ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||1||C1||-|| 87 87 ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||1||C1||Liquid N2 fill in the cleanroom|| 88 88 ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Verification of the operability of the motors and light sources]||Day||0.5||C1||optical bench needed in the cleanroom, Liquid N2 fill in the cleanroom|| … … 90 90 ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||1||C1||Liquid N2 fill in the cleanroom|| 91 91 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||LBTO SW support maybe required, Liquid N2 fill in the cleanroom|| 92 ||Total||Contingency included within|| ||1 1.5|| || ||92 ||Total||Contingency included within|| ||12.5|| || || 93 93 94 94 === Phase 2 (Pre-commissioning)===