97 | | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C1A||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document, AD3, for more details.|| |
98 | | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C1A||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document, AD3, for more details.|| |
| 97 | ||P2.0A||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform - 1]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C2||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document, AD3, for more details.|| |
| 98 | ||P2.0B||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform - 2]||Day||1||C2||Support for the installation and checking of electronics cabinets, cabling, and their checking, safety officer, working platform installed in front of the Gregorian focal-station SX, check the installation document, AD3, for more details.|| |