81 | | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes and their visual inspection]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support unpacking and moving|| |
82 | | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Install the instrument in the cleanroom with its electronics cabinet]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure, Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.|| |
| 81 | ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes, their visual inspection, and mounting the units on the handling]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support unpacking and moving|| |
| 82 | ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay & cleanroom), 1-2 crew to support installation on the mechanical structure, Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed.|| |