95 | | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details|| |
| 95 | ||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document, AD3, for more details.|| |