    8888=== Phase 1 ===
    8989'''SHARK-NIR Location''' : LBT mountain bay and clean room
    90 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (mins)'''||'''Maximum Duration (mins)'''||'''Category'''||'''LBTO Support'''||                     
    91 ||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||40||40||C1||-||
    92 ||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes and their visual inspection]||Day||60||60||C1||crane operator to lift and move containers/boxes, 1-2 crew to support unpacking and moving||
    93 ||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Install the instrument in the cleanroom with its electronics cabinet]||Day||240||240||C1||crane operator to lift and move containers/boxes, 1-2 crew to support installation on the mechanical structure||
    94 ||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, and connect to LBT network]||Day||120||120||C1||support to connect to LBT network? Any electronics support?||
    95 ||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||20||20||C1||-||
    96 ||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||480||480||C1||Liquid N2 fill||
    97 ||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Verification of the operability of the motors and light sources]||Day||60||60||C1||-||
    98 ||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||120||120||C1||-||
    99 ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||60||60||C1||-||
     90||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||                     
     91||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||40||C1||-||
     92||P1.2||[wiki:/docs/CommissioningPlan/P1.2 Opening boxes and their visual inspection]||Day||60||C1||crane operator to lift and move containers/boxes, 1-2 crew to support unpacking and moving||
     93||P1.3||[wiki:/docs/CommissioningPlan/P1.3 Install the instrument in the cleanroom with its electronics cabinet]||Day||240||C1||crane operator to lift and move containers/boxes, 1-2 crew to support installation on the mechanical structure||
     94||P1.4||[wiki:/docs/CommissioningPlan/P1.4 Cable in the instrument, power on, and connect to LBT network]||Day||120||C1||support to connect to LBT network? Any electronics support?||
     95||P1.5||[wiki:/docs/CommissioningPlan/P1.5 Start all the services and initialize all the motors]||Day||20||C1||-||
     96||P1.6||[wiki:/docs/CommissioningPlan/P1.6 Cool down the cryostat]||Day||480||C1||Liquid N2 fill||
     97||P1.7||[wiki:/docs/CommissioningPlan/P1.7 Verification of the operability of the motors and light sources]||Day||60||C1||-||
     98||P1.8||[wiki:/docs/CommissioningPlan/P1.8 Verification of the internal alignment of the instrument]||Day||120||C1||-||
     99||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||60||C1||-||
    100100
    101101=== Phase 2 ===
    102102'''SHARK-NIR Location''' : LBT platform
    103 ||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (mins)'''||'''Maximum Duration (mins)'''||'''Category'''||'''LBTO Support'''||     
    104 ||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||60      ||60||C2||Verify the working of emergency button||
    105 ||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and performance]||Day||180||180||C2||-||
    106 ||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||60||60||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriter||
    107 ||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||120||120||C2||Mounting RR on the SX side. Support from LBTI?||
    108 ||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Synergy with LBTI AO system test]||Day||120||120||C2||Mounting RR on the SX side. Support from LBTI for AO running||
    109 ||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||180||180||C3||Mounting RR on the SX side, Support from LBTI for AO running||
    110 ||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features]||Day||60||60||C2||Support from LBTI for AO running||
    111 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||180||180||C2||Support from LBTI for AO running||
    112 ||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Nighttime acquisition and setting telescope collimation for night]||Night||180||180||C4||Support from LBTI for AO running||
     103||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (d)'''||days||'''Category'''||'''LBTO Support'''|| 
     104||P2.1||[wiki:/docs/CommissioningPlan/P2.1 Activating the instrument and testing instrument states & transitions]||Day||1|||C2||Verify the working of emergency button||
     105||P2.2||[wiki:/docs/CommissioningPlan/P2.2 Instrument operability and performance]||Day||180||C2||-||
     106||P2.3||[wiki:/docs/CommissioningPlan/P2.3 TCS communication test]||Day||60||C2||Authorise SHARK-NIR, connecting to ASM+LBTI AO system, able to send preset, receiving LBT telemetry and details for the fitswriter||
     107||P2.4||[wiki:/docs/CommissioningPlan/P2.4 Align SHARK-NIR to the telescope]||Day||120||C2||Mounting RR on the SX side. Support from LBTI?||
     108||P2.5||[wiki:/docs/CommissioningPlan/P2.5 Synergy with LBTI AO system test]||Day||120||C2||Mounting RR on the SX side. Support from LBTI for AO running||
     109||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||180||C3||Mounting RR on the SX side, Support from LBTI for AO running||
     110||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Looking for filter defects/effects/features]||Day||60||C2||Support from LBTI for AO running||
     111||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Flexure tests]||Day||180||C2||Support from LBTI for AO running||
     112||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Nighttime acquisition and setting telescope collimation for night]||Night||0.5||C4||Support from LBTI for AO running||
    113113
    114114=== Phase 3 ===