Changes between Version 118 and Version 119 of docs/CommissioningPlan
- Timestamp:
- 01/25/21 12:59:48 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan
v118 v119 88 88 ||P1.9||[wiki:/docs/CommissioningPlan/P1.9 Science detector calibrations]||Day||1||C1||Liquid N2 fill in the cleanroom|| 89 89 ||P1.10||[wiki:/docs/CommissioningPlan/P1.10 Testing of SCICAM image grabbing by SOUL-AO]||Day||2||C1||LBTO SW support maybe required, Liquid N2 fill in the cleanroom|| 90 ||Total||Conti gency of 1 day|| ||11+1=12|| || ||90 ||Total||Contingency included within|| ||11|| || || 91 91 92 92 === Phase 2 (Pre-commissioning)===