  • docs/CommissioningPlan

    v114 v115  
    109109=== Phase 3 (Commissioning)===
    110110'''SHARK-NIR Location''': LBT platform. All nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.
     111
     112Every evening of the nighttime commissioning, all the required calibrations (including dark, bias, flat-field, etc. for all the filters required) will be taken using the SHARK-NIR calibration unit.
    111113||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (hours)'''||'''Category'''||'''LBTO Support'''||
    112114||P3.0||[wiki:/docs/CommissioningPlan/P3.0 Large spatial scale instrument and telescope flat field]||Twilight||2||C5||-||
     
    134136=== Phase 4 (Science Verification / Early Science)===
    135137'''SHARK-NIR Location''' : LBT platform.  All nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. SHINS is tested and working properly. Only tweaking or parameter adjustment, if any, is expected from SHINS at this stage.
     138
     139Every evening of the nighttime commissioning, all the required calibrations (including dark, bias, flat-field, etc. for all the filters required) will be taken using the SHARK-NIR calibration unit.
    136140||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (nights)'''||'''Category'''||'''LBTO Support'''||
    137141||P4.1||[wiki:/docs/CommissioningPlan/P4.1 Direct imaging + field stabilized mode testing]||Night||1.5||C4 + C6||AO support||