Changes between Version 113 and Version 114 of docs/CommissioningPlan


Ignore:
Timestamp:
01/20/21 15:19:01 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan

    v113 v114  
    101101||P2.6||[wiki:/docs/CommissioningPlan/P2.6 Measurement of NCPA]||Day||5+5||C2 + C3||Authorize SHARK-NIR on SX side. Permission to use the Argos Swing Arm. When not using Argos swing arm and for different elevation angle tests, RR will be required on the SX side. Support from LBT SW Team, LBTI/Arcetri team to run SOUL AO||
    102102||P2.7||[wiki:/docs/CommissioningPlan/P2.7 Checking pointing offset between SHARK-NIR and SOUL-AO]||Day||3||C2||Mounting RR on the SX side. Support on running SOUL AO||
    103 ||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Looking for filter defects/effects/features+ Science detector calibrations repeat]||Day||2||C2||Mounting RR on the SX side. Support on running SOUL AO||
     103||P2.8||[wiki:/docs/CommissioningPlan/P2.8 Looking for filter defects/effects/features + Science detector calibrations repeat]||Day||2||C2||Mounting RR on the SX side. Support on running SOUL AO||
    104104||P2.9||[wiki:/docs/CommissioningPlan/P2.9 Flexure tests]||Day||3||C2 + C3||Mounting RR on the SX side. Support on running SOUL AO, the telescope need to move in elevation||
    105105||P2.10||[wiki:/docs/CommissioningPlan/P2.10 Cryostat warm up check]||Day||2||C2||-||
     
    108108
    109109=== Phase 3 (Commissioning)===
    110 '''SHARK-NIR Location''': LBT platform. Mostly nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.
     110'''SHARK-NIR Location''': LBT platform. All nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.
    111111||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (hours)'''||'''Category'''||'''LBTO Support'''||
    112112||P3.0||[wiki:/docs/CommissioningPlan/P3.0 Large spatial scale instrument and telescope flat field]||Twilight||2||C5||-||
     
    133133
    134134=== Phase 4 (Science Verification / Early Science)===
    135 '''SHARK-NIR Location''' : LBT platform.  Almost all nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. SHINS is tested and working properly. Only tweaking or parameter adjustment, if any, is expected from SHINS at this stage.
     135'''SHARK-NIR Location''' : LBT platform.  All nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. SHINS is tested and working properly. Only tweaking or parameter adjustment, if any, is expected from SHINS at this stage.
    136136||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (nights)'''||'''Category'''||'''LBTO Support'''||
    137137||P4.1||[wiki:/docs/CommissioningPlan/P4.1 Direct imaging + field stabilized mode testing]||Night||1.5||C4 + C6||AO support||