    44This commissioning planning document lays out and details the activities needed to bring SHARK-NIR online for regular scientific exploitation. The document incorporates activities starting from the unpacking of the boxes at the LBT mountain bay to the early science /science verification at its final destination on the LBT platform. Although called the commissioning document, it lists the pre-commissioning, commissioning, and science verification activities.
    55
    6 The commissioning is broadly divided into four phases:
     6The activities are classified into four phases:
    77 **Phase 1**: We start by inspecting the boxes at LBT mountain bay, unpacking, and installing the instrument at the mountain lab (clean room) for alignment verification and functionality checks. All of these are daytime activities. [Pre-commissioning: Unpack, assemble, and clean-room verification]
    88