    1111 **Phase 3**: Phase 3 commences the nighttime commissioning, starting from sending preset to the telescope to testing individual SHARK-NIR observation modes for performance to the total SHARK-NIR performance. All the activities are nighttime. However, some daytime activities may be anticipated as well. By the end of this phase, SHARK-NIR is ready for early science observations. [Commissioning]
    1212
    13  **Phase 4**: SHARK-NIR is ready for the final phase of the commissioning - the science verification / early science observations. The final form of the SHARK-NIR software, observing blocks, data-reduction pipeline, etc. will be tested for all the modes (and sub-modes) of the instrument. The final performance of the SHARK-NIR will be analyzed using the data from this run. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for regular science operations (with some 'risk' of course for another year). [Science Verification / Early Science]
     13 **Phase 4**: SHARK-NIR is ready for the final phase of the commissioning - the science verification / early science observations. The final form of the SHARK-NIR software, observing blocks, data-reduction pipeline, etc., will be tested for all the modes (and sub-modes) of the instrument. The final performance of the SHARK-NIR will be analyzed using the data from this run. All the activities are nighttime. By the end of this phase, SHARK-NIR is ready for regular science operations (with some 'risk,' of course, for another year). [Science Verification / Early Science]
    1414
    1515
     
    4343  - category : one of the categories mentioned above
    4444  - recurrence : describes how frequently the test must be executed
    45   - duration : estimates the time required to complete the test (the duration mentioned here is valid only for commissioning)
     45  - duration: estimates the time required to complete the test (the duration mentioned here is valid only for commissioning)
    4646
    4747Description
     
    7676
    7777=== Phase 1 (Pre-commissioning)===
    78 '''SHARK-NIR Location''' : LBT mountain bay and clean room (Some of the activities may run in parallel). All daytime activities.
     78'''SHARK-NIR Location''': LBT mountain bay and clean room (Some of the activities may run in parallel). All daytime activities.
    7979||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||                     
    8080||P1.1||[wiki:/docs/CommissioningPlan/P1.1 Inspection of the boxes]||Day||0.5||C1||crane operator to lift and move containers/boxes (mountain bay), 1-2 crew to support moving||
     
    9191
    9292=== Phase 2 (Pre-commissioning)===
    93 '''SHARK-NIR Location''' : LBT platform (Some of the activities may run in parallel). All daytime activities.
     93'''SHARK-NIR Location''': LBT platform (Some of the activities may run parallel). All daytime activities.
    9494||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (days)'''||'''Category'''||'''LBTO Support'''||     
    9595||P2.0||[wiki:/docs/CommissioningPlan/P2.0 Installation of the SHARK-NIR at LBT platform]||Day||2(preparation) + 1(lift-off) + 1(contingency)||C1||Crew members' support for the preparation, lift-off, and installation of SHARK-NIR, crane operator (mountain bay, LBT platform), safety officer, working platform installed in front of the Gregorian focal-station SX, installation of electronics in LBTI/SHARK cabinet, check the installation document for more details||
     
    108108
    109109=== Phase 3 (Commissioning)===
    110 '''SHARK-NIR Location''' : LBT platform. Mostly nightime activities. Some daytime support (within SHARK-NIR) is anticipated. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.
     110'''SHARK-NIR Location''': LBT platform. Mostly nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. Also, the SHARK-NIR software, SHINS, is expected to be almost ready to be tested.
    111111||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (hours)'''||'''Category'''||'''LBTO Support'''||
    112112||P3.0||[wiki:/docs/CommissioningPlan/P3.0 Large spatial scale instrument and telescope flat field]||Twilight||2||C5||-||
     
    132132
    133133=== Phase 4 (Science Verification / Early Science)===
    134 '''SHARK-NIR Location''' : LBT platform.  Almost all nightime activities. Some daytime support (within SHARK-NIR) is anticipated. SHINS is tested and working properly. Only tweaking or parameter adjustment, if any, is expected from SHINS at this stage.
     134'''SHARK-NIR Location''' : LBT platform.  Almost all nighttime activities. Some daytime support (within SHARK-NIR) is anticipated. SHINS is tested and working properly. Only tweaking or parameter adjustment, if any, is expected from SHINS at this stage.
    135135||'''Number'''||'''Activity Name'''||'''Day / Night'''||'''Duration (nights)'''||'''Category'''||'''LBTO Support'''||
    136136||P4.1||[wiki:/docs/CommissioningPlan/P4.1 Direct imaging + field stabilized mode testing (95% cases)]||Night||1.5||C4 + C6||AO support||
     
    139139||P4.4||[wiki:/docs/CommissioningPlan/P4.3 Coronagraphic imaging + pupil stabilization mode testing]||Night||3||C4 + C6||AO support||
    140140||P4.5||[wiki:/docs/CommissioningPlan/P4.4 Long-slit spectrograph mode testing]||Night||2||C4 + C6||AO support||
    141 ||P4.7||[wiki:/docs/CommissioningPlan/P4.6 Exo-planet: Giant planets and brown dwarfs in SFR, stellar associations, & young open clusters]||Night||10||C4 + C6||AO support||
    142 ||P4.8||[wiki:/docs/CommissioningPlan/P4.7 Exo-planet: Astrometry]||Night||4||C4 + C6||AO support||
    143 ||P4.9||[wiki:/docs/CommissioningPlan/P4.8 Exo-planet: Spectroscopic Characetization of known sub-stellar companions]||Night||5||C4 + C6||AO support||
    144 ||P4.10||[wiki:/docs/CommissioningPlan/P4.9 Disk: High-contrast images of circumstellar disks]||Night||1||C4 + C6||AO support||
    145 ||P4.11||[wiki:/docs/CommissioningPlan/P4.10 Disk: Coronagraphic imaging of stellar jets]||Night||1||C4 + C6||AO support||
    146 ||P4.12||[wiki:/docs/CommissioningPlan/P4.11 Disk:  Jets investigated with long-slit spectra]||Night||1||C4 + C6||AO support||
    147 ||P4.13||[wiki:/docs/CommissioningPlan/P4.12 Extragalactic: QSO & AGNs]||Night||4||C4 + C6||AO support||
    148 ||P4.14||[wiki:/docs/CommissioningPlan/P4.13 Solar system: Size and shape of main-belt astroids]||Night||1||C4 + C6||AO support||
    149 ||P4.15||[wiki:/docs/CommissioningPlan/P4.14 Solar system: Surface heterogeneity of trans-neptunian objects]||Night||1||C4 + C6||AO support||
     141||P4.6||[wiki:/docs/CommissioningPlan/P4.6 Exo-planet: Giant planets and brown dwarfs in SFR, stellar associations, & young open clusters]||Night||10||C4 + C6||AO support||
     142||P4.7||[wiki:/docs/CommissioningPlan/P4.7 Exo-planet: Astrometry]||Night||4||C4 + C6||AO support||
     143||P4.8||[wiki:/docs/CommissioningPlan/P4.8 Exo-planet: Spectroscopic Characterization of known sub-stellar companions]||Night||5||C4 + C6||AO support||
     144||P4.9||[wiki:/docs/CommissioningPlan/P4.9 Disk: High-contrast images of circumstellar disks]||Night||1||C4 + C6||AO support||
     145||P4.10||[wiki:/docs/CommissioningPlan/P4.10 Disk: Coronagraphic imaging of stellar jets]||Night||1||C4 + C6||AO support||
     146||P4.11||[wiki:/docs/CommissioningPlan/P4.11 Disk:  Jets investigated with long-slit spectra]||Night||1||C4 + C6||AO support||
     147||P4.12||[wiki:/docs/CommissioningPlan/P4.12 Extragalactic: QSO & AGNs]||Night||4||C4 + C6||AO support||
     148||P4.13||[wiki:/docs/CommissioningPlan/P4.13 Solar system: Size and shape of main-belt astroids]||Night||1||C4 + C6||AO support||
     149||P4.14||[wiki:/docs/CommissioningPlan/P4.14 Solar system: Surface heterogeneity of trans-neptunian objects]||Night||1||C4 + C6||AO support||
    150150
    151151Note: The duration mentioned in Phase 4 will be changed to hours later.
     
    160160
    161161=== MDP
    162 - all operation that should be supported by **control software** automated procedures should be defined by the responsible person with software person in copy or in accordance with software department (better) (e.g.: P1.8 and P1.9)
     162- all operation that should be supported by **control software** automated procedures should be defined by the responsible person with software person in copy or accordance with software department (better) (e.g., P1.8 and P1.9)
    163163 
    164164=== Reminders