    11 == SDC3        Wavelength calibration ==
    2 •       **Phase**               :       Any 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Daytime calibration (C3)
    5 •       **Recurrence**  :       every night when LSS observing mode is used.
    6 •       **Duration**            :       10 minutes
     2
     3- **Phase**             :       Any 
     4- **Status**            :       Draft   
     5- **Category**  :       Daytime calibration (C3)
     6- **Recurrence**        :       every night when LSS observing mode is used.
     7- **Duration**  :       10 minutes
     8
    79**Description**
    8 •       Determine the central wavelength of each pixel for the long split spectroscopy observing mode.
     10- Determine the central wavelength of each pixel for the long split spectroscopy observing mode.
     11
    912**Prerequisites**
    10 •       Authorize SHARK-NIR on the SX side.
    11 •       Atmospheric conditions: AO working conditions.
    12 •       Bad pixel map, Background or Dark, Flat-field, distortion map
     13- Authorize SHARK-NIR on the SX side.
     14- Atmospheric conditions: AO working conditions.
     15- Bad pixel map, Background or Dark, Flat-field, distortion map
     16
    1317**Procedure**
    14 •       This calibration is performed illuminating the slit with the spectral calibration lamps with at least 5 known emission lines; background exposures with lamps switched off required.
     18- This calibration is performed illuminating the slit with the spectral calibration lamps with at least 5 known emission lines; background exposures with lamps switched off are required.
     19
     20** Templates**
     21
    1522**Success criteria**
    16 •       LRS: 10 nm (goal 5 nm), MRS: 1 nm.
     23- LRS: 10 nm (goal 5 nm), MRS: 1 nm.
     24
    1725**Notes**
    18 •       Same as activity 7.10 in AD4
     26- Same as activity 7.10 in AD4
     27
    1928**LBTO support**
    2029
    21 **Associated SHARK-NIR personnel**
    22 
    2330**Date performed and by whom**