P3.4 PSF Alignment
- Phase : 3
- Status : COMPLETE, to be done for SP-2, SP-3, FQPM, and SLIT-2
- Category : Nighttime testing (functionality and operability) (C5) + Nighttime calibration (C6)
- Recurrence : before every observing target (CI, LSS), starting from commissioning.
- Duration : 2 hours
Description
- Alignment of the PSF with occulter (or slit) in coronagraphic mode.
Prerequisites
- Bad pixel map, Background or Dark, Flat-field, detector RON
Procedure The internal deformable mirror's position (TTM_DM) is optimized to have the PSF image on the intermediate focal plane centered with the occulter. We compare the PSF center, measured on the SCICAM, with the center of the occulter measured on the SCICAM using the calibration flat-field source.
Templates
- SHARKNIR_gen_tec_PSFAlignment
Success criteria
- delta between PSF center and occulter center < 0.2 pixels.
Notes
- Same as activity 8.3 in AD4
- 7 cases, 30 mins per case.
LBTO support
- AO support
Date performed and by whom