    44•       **Category**            :       Nighttime testing (functionality and operability) (C4)
    55•       **Recurrence**  :       before every observing target (CI, LSS), starting from commissioning.
    6 •       **Duration**            :       30 minutes
     6•       **Duration**            :       2.5 hours
    77**Description**
    8 •       Alignment of the internal pupil image (PP1) with apodizer in the coronagraphic mode
     8•       Alignment of the internal pupil image (PP1)with apodizer  [and Lyot stop at PP2]in the coronagraphic mode
    99**Prerequisites**
    1010•       Bad pixel map, Background or Dark, Flat-field, detector RON
     
    2222
    2323**Date performed and by whom**
     24
     25**Comment**