    22•       **Phase**               :       3 
    33•       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C4)
     4•       **Category**            :       Nighttime testing (functionality and operability) (C5) + Nighttime calibration (C6)
    55•       **Recurrence**  :       before every observing target (CI, LSS), starting from commissioning.
    6 •       **Duration**            :       2.5 hours
     6•       **Duration**            :       1 night
    77**Description**
    88•       Alignment of the internal pupil image with apodizer (at PP1) or Lyot stop (at PP2) in the coronagraphic mode