== P2.5 SOUL-AO verification == • **Phase** : 2 • **Status** : Draft • **Category** : Daytime testing (functionality and operability) (C2) • **Recurrence** : after instrument installation at telescope platform • **Duration** : 3 hours **Description** • Proper working and tuning of the SOUL-AO parameters is verified. If any minor adjustments are required, they are either implemented immediately or marked for a later daytime work. **Prerequisites** * Activities [wiki:/docs/CommissioningPlan/P1.9 P1.9]and [wiki:/docs/CommissioningPlan/P2.5 P2.5] are successfully completed. **Procedure** • AO veririfaction procedure comes here ? **Success criteria** • SOUL AO system working in tandem with the SHARK-NIR system. • Acceptable improvement of the on-axis PSF for a given seeing and brightness of the star. **Notes** **LBTO support** Support on running SOUL-AO **Associated SHARK-NIR personnel** **Date performed and by whom**