Changes between Version 1 and Version 2 of docs/CommissioningPlan/P3.32
- Timestamp:
- 01/19/21 14:28:51 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P3.32
v1 v2 1 == P3. 32PSF Alignment ==1 == P3.6 PSF Alignment == 2 2 • **Phase** : 3 3 3 • **Status** : Draft 4 4 • **Category** : Nighttime testing (functionality and operability) (C4) 5 5 • **Recurrence** : before every observing target (CI, LSS), starting from commissioning. 6 • **Duration** : <5minutes6 • **Duration** : 30 minutes 7 7 **Description** 8 8 • Alignment of the PSF with occulter (or slit) in coronagraphic mode. … … 16 16 • Same as activity 8.3 in AD4 17 17 **LBTO support** 18 • S upport from LBTI/LBTO?18 • SOUL-AO support 19 19 **Associated SHARK-NIR personnel** 20 • JF, LM, MdP 20 21 21 **Date performed and by whom**