Changes between Version 1 and Version 2 of docs/CommissioningPlan/P3.32


Ignore:
Timestamp:
01/19/21 14:28:51 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P3.32

    v1 v2  
    1  == P3.32       PSF Alignment ==
     1 == P3.6        PSF Alignment ==
    22•       **Phase**               :       3 
    33•       **Status**              :       Draft   
    44•       **Category**            :       Nighttime testing (functionality and operability) (C4)
    55•       **Recurrence**  :       before every observing target (CI, LSS), starting from commissioning.
    6 •       **Duration**            :       <5 minutes
     6•       **Duration**            :       30 minutes
    77**Description**
    88•       Alignment of the PSF with occulter (or slit) in coronagraphic mode.
     
    1616•       Same as activity 8.3 in AD4
    1717**LBTO support**
    18 •       Support from LBTI/LBTO?
     18•       SOUL-AO support
    1919**Associated SHARK-NIR personnel**
    20 •       JF, LM, MdP
     20
    2121**Date performed and by whom**