Changes between Version 2 and Version 3 of docs/CommissioningPlan/P3.2
- Timestamp:
- 01/19/21 14:05:59 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P3.2
v2 v3 4 4 • **Category** : Nighttime testing (functionality and operability) (C4) 5 5 • **Recurrence** : once at commissioning 6 • **Duration** : 1 night6 • **Duration** : 1 hour 7 7 **Description** 8 8 • For the correct telescope mode for SHARK-NIR, find the offset direction & magnitude (for the field-stabilized mode), verify the proper image orientation, pixel scale, field of view, and distortion at the SCICAM. Note that this may be performed with and without AO running.