    v2 v3  
    44•       **Category**            :       Nighttime testing (functionality and operability) (C4)
    55•       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       1 night
     6•       **Duration**            :       1 hour
    77**Description**
    88•       For the correct telescope mode for SHARK-NIR, find the offset direction & magnitude (for the field-stabilized mode), verify the proper image orientation, pixel scale, field of view, and distortion at the SCICAM. Note that this may be performed with and without AO running.