wiki:docs/CommissioningPlan/P3.18

Version 9 (modified by dvassall, 15 months ago) (diff)

--

P3.18 Point the slit

  • Phase : 3
  • Status : Draft
  • Category : Nighttime testing (functionality and operability) (C5)
  • Recurrence : once at commissioning
  • Duration : 2 nights

Description

  • This activity will point the long slit in the (known) direction of an off-axis source.

Prerequisites

  • Atmospheric conditions: AO working conditions.
  • Authorize SHARK-NIR on the SX side.

Procedure

  • Preset to a known binary, center the slit on one of stars and then point the slit at the nominal (known) position of the companion by using the instrument derotator.

Templates

  • SHARKNIR_gen_tec_PSFAlignment

Success criteria

  • xxx

Notes

LBTO support

  • AO support

Date performed and by whom