P3.18 Center the slit
- Phase : 3
- Status : Draft
- Category : Nighttime testing (functionality and operability) (C5)
- Recurrence : once at commissioning
- Duration : 2 nights
Description
- This activity will center the long slit.
Prerequisites
- Atmospheric conditions: AO working conditions.
- Authorize SHARK-NIR on the SX side.
Procedure
- Point to known binary stars and then offset the telescope and the rotators to get to the nominal (known) position of the planet or introducing a bright speckle by using secondary mirrors at the same parallactic angle of the planet in order to align the slit.
- TBD
Templates
Success criteria
- xxx
Notes
LBTO support
- AO support
Date performed and by whom