  • docs/CommissioningPlan/P3.13

    v5 v6  
    22•       **Phase**               :       3 
    33•       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C4)
     4•       **Category**            :       Nighttime testing (functionality and operability) (C5)
    55•       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       4 hours
     6•       **Duration**            :       2 nights
    77**Description**
    88•       This activity will center the long slit.
     
    1111•       Authorize SHARK-NIR on the SX side.
    1212**Procedure**
    13 •       Point to known binary stars and then offset the telescope and the rotators to get to the nominal (known) position of the planet or introducing a bright speckle by using secondary mirrors at the same parallactic angle of the planet in order to align the slit or TBD????? [This procedure is not complete. we need to work on this.]
     13•       Point to known binary stars and then offset the telescope and the rotators to get to the nominal (known) position of the planet or introducing a bright speckle by using secondary mirrors at the same parallactic angle of the planet in order to align the slit.
     14* TBD
    1415**Success criteria**
    1516•       xxx
    1617**Notes**
     18
    1719**LBTO support**
    1820•       SOUL-AO support