| 1 | == P3.13 Center the slit == |
| 2 | • **Phase** : 3 |
| 3 | • **Status** : Draft |
| 4 | • **Category** : Nighttime testing (functionality and operability) (C4) |
| 5 | • **Recurrence** : once at commissioning |
| 6 | • **Duration** : 40 minutes |
| 7 | **Description** |
| 8 | • This activity will center the long slit. |
| 9 | **Prerequisites** |
| 10 | • Atmospheric conditions: AO working conditions. |
| 11 | • Authorize SHARK-NIR on the SX side. |
| 12 | **Procedure** |
| 13 | • Point to known binary stars and then offset the telescope and the rotators to get to the nominal (known) position of the planet or introducing a bright speckle by using secondary mirrors at the same parallactic angle of the planet in order to align the slit or TBD????? |
| 14 | **Success criteria** |
| 15 | • xxx |
| 16 | **Notes** |
| 17 | **LBTO support** |
| 18 | • Support from LBTI/LBTO? |
| 19 | **Associated SHARK-NIR personnel** |
| 20 | • JF, LM, MdP |
| 21 | **Date performed and by whom** |