    1 == P3.11        Check the acquisition procedure ==
    2 •       **Phase**               :       3 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C5)
    5 •       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       4 hours
     1 == P3.11        Sky background ==
     2 
     3- **Phase**             :       3 
     4- **Status**            :       Draft   
     5- **Category**  :       Nighttime testing (functionality and operability) (C5) + Nighttime calibration (C6)
     6- **Recurrence**        :       once at commissioning and then on request.
     7- **Duration**  :       2 hours
     8
    79**Description**
    8 •       Verify the acquisition sequence for SHARK-NIR
     10- Acquire a series of sky backgrounds from science images. A short sky background may also be useful for remaining deviant pixel removal.
     11
    912**Prerequisites**
    10 •       Atmospheric conditions: should be able to see bright stars in the sky (preferably close to zenith?).
    11 •       Authorize SHARK-NIR on the SX side.
    12 •       Suitable bright enough target (including the possibility of performing AO).
     13- Authorize SHARK-NIR on the SX side.
     14- Atmospheric conditions: AO working conditions???
     15
    1316**Procedure**
    14 •       Start the acquisition sequence: collimating the telescope to reduce the aberrations, close the loop and produce better ASM flat, NCPA estimation using phase-diversity algorithm, close SHARK-NIR tip-tilt+NCPA loop, and check the PSF quality at SCICAM.
    15 •       Save telemetry (open and closed loop of the ALPAO DM).
     17- Observe a blank field close to the science target (separation~10-20 arcsec)
     18- The same set-up as nighttime science observations, but AO is not running, and the coronagraph may be removed. A list of telescope offsets is added to reach an “empty” field and jitter.
     19
     20**Templates**
     21
    1622**Success criteria**
    17 •       Successful acquisition sequence.
     23- 10% accuracy (dependent on measurement frequency)
     24
    1825**Notes**
     26- Same as activity 7.6 in AD4
     27
    1928**LBTO support**
    20 •       AO support
    21 
    22 **Associated SHARK-NIR personnel**
    2329
    2430**Date performed and by whom**