  • docs/CommissioningPlan/P3.11

    v2 v3  
    22•       **Phase**               :       3 
    33•       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C4)
     4•       **Category**            :       Nighttime testing (functionality and operability) (C5)
    55•       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       2 hours
     6•       **Duration**            :       2 nights
    77**Description**
    88•       Verify the acquisition sequence for SHARK-NIR
    99**Prerequisites**
    10 •       Atmospheric conditions: should be able to see bight stars on sky (preferably close to zenith?).
     10•       Atmospheric conditions: should be able to see bright stars in the sky (preferably close to zenith?).
    1111•       Authorize SHARK-NIR on the SX side.
    1212•       Suitable bright enough target (including the possibility of performing AO).