  • Phase : 3
  • Status : Draft
  • Category : Nighttime testing (functionality and operability) (C4)
  • Recurrence : once at commissioning
  • Duration : 12 hours

Description

  • Evaluate the NCPA working and performance using the baseline approach, phase-diversity approach using the Wollaston prism & dual-band imaging, and measurement of NCPA using SHARK-NIR internal calibration sources.

Prerequisites

  • Atmospheric conditions: ?
  • Authorize SHARK-NIR on the SX side.
  • AO working.
  • Target(s) at different Zenith distances with different magnitudes?

Procedure

  • Acquire star of a given magnitude. Start SOUL-AO.
  • Check the working and performance of the NCPA (already calibrated) baseline approach. Take images at SCICAM.
  • Check the phase diversity NCPA approach using Wollaston prism + DI-DBI (need to do on the spot, but script exists). Take images at SCICAM.
  • Check the phase diversity approach using the internal calibration source (already calibrated). Take images at SCICAM.
  • Repeat for a different star (of different magnitudes and for a different elevation of the telescope). It is also good to do this for different seeing conditions.

Success criteria

  • NCPA estimated and applied on the ASM / ALPAO DM.
  • Cross-check the NCPA performances with the daytime activity P2.6.
  • The total residual after NCPA correction should be <30nm.