Version 8 (modified by kradhakrishnan, 4 years ago) (diff) |
---|
P3.10 NCPA working and performance
- Phase : 3
- Status : Draft
- Category : Nighttime testing (functionality and operability) (C4)
- Recurrence : once at commissioning
- Duration : 12 hours
Description
- Evaluate the NCPA working and performance using the baseline approach, phase-diversity approach using the Wollaston prism & dual-band imaging, and measurement of NCPA using SHARK-NIR internal calibration sources.
Prerequisites
- Atmospheric conditions: ?
- Authorize SHARK-NIR on the SX side.
- AO working.
- Target(s) at different Zenith distances with different magnitudes?
Procedure
- Acquire star of a given magnitude. Start SOUL-AO.
- Check the working and performance of the NCPA (already calibrated) baseline approach. Take images at SCICAM.
- Check the phase diversity NCPA approach using Wollaston prism + DI-DBI (need to do on the spot, but script exists). Take images at SCICAM.
- Check the phase diversity approach using the internal calibration source (already calibrated). Take images at SCICAM.
- Repeat for a different star (of different magnitudes and for a different elevation of the telescope). It is also good to do this for different seeing conditions.
Success criteria
- NCPA estimated and applied on the ASM / ALPAO DM.
- Cross-check the NCPA performances with the daytime activity P2.6.
- The total residual after NCPA correction should be <30nm.
Notes
LBTO support
- SOUL-AO support
Associated SHARK-NIR personnel
Date performed and by whom