Version 13 (modified by kradhakrishnan, 4 years ago) (diff) |
---|
P3.10 NCPA working and performance & checking for pupil shifts
- Phase : 3
- Status : Draft
- Category : Nighttime testing (functionality and operability) (C5) + Nighttime testing for performance (C7)
- Recurrence : once at commissioning
- Duration : 3 nights
Description
- Evaluate the NCPA working and performance using the baseline approach, phase-diversity approach using the Wollaston prism & dual-band imaging, and measurement of NCPA using SHARK-NIR internal calibration sources.
Prerequisites
- Atmospheric conditions: TBD
- Authorize SHARK-NIR on the SX side.
- AO working.
- Target(s) at different Zenith distances with different magnitudes?
Procedure
- Acquire star of a given magnitude. Start SOUL-AO.
- Check the working and performance of the NCPA (already calibrated) baseline approach. Take images at SCICAM.
- Check the phase diversity NCPA approach using Wollaston prism + DI-DBI (already calibrated). Take images at SCICAM.
- Measure the phase diversity NCPA approach using Wollaston prism + DI-DBI and using real star (need to do on the spot, but script exists). Take images at SCICAM.
- Digression: If the PSF after applying the calibrated NCPA is bad, we could close the SHARK-NIR shutter (can have the SOUL-AO running parallel) and do a quick internal NCPA measurement (either till the NCPA modal coefficients or until the new shape on ALPAO-DM). Confirm that the alignment of SHARK-NIR is still good.
- Check the pupil position inserting the pupil lens.
- Repeat for a different star (of different magnitudes and for a different elevation of the telescope). It is also good to do this for different seeing conditions.
Success criteria
- NCPA estimated and applied on the ASM / ALPAO DM.
- Cross-check the NCPA performances with the daytime activity P2.6.
- The total residual after NCPA correction should be <30nm.
Notes
LBTO support
- AO support
Associated SHARK-NIR personnel
Date performed and by whom