Changes between Version 5 and Version 6 of docs/CommissioningPlan/P3.10


Ignore:
Timestamp:
01/26/21 11:07:34 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P3.10

    v5 v6  
    66•       **Duration**            :       12 hours
    77**Description**
    8 •       Evaluate the NCPA working and performance using the baseline approach, phase-diversity approach, combination of both, and measurement of NCPA using the Wollaston prison & dual-band imaging.
     8•       Evaluate the NCPA working and performance using the baseline approach, phase-diversity approach using the Wollaston prism & dual-band imaging, and measurement of NCPA using SHARK-NIR internal calibration sources.
    99
    1010**Prerequisites**